Emergency repair for a paper mill water box
A corroded chiller water box was rebuilt and returned in about 36 hours, at roughly 30% of the cost of a new one.



The divider bar on a small but critical chiller water box located at a paper mill had completely corroded and was no longer functional in the process equipment it served. The mill's options to solve this problem were limited.
The lead time for a new water box was 5-6 weeks, and the mill's engineers were not willing to make emergency on-the-spot weld repairs because of safety concerns when the equipment is put back into service. ENECON was contacted to provide a solution to this emergency situation.
The water box was degreased, pressure washed, and then abrasive-blasted. METALCLAD DurAlloy and a backer plate were used to rebuild the divider bar.
One coat of METALCLAD CeramAlloy CL+AC in gray was used on the internal side, followed by a second coat in blue to finish the interior as well as the exterior of the water box.
The water box was completed and returned approximately 36 hours after it was first collected. The mill was very pleased with the turnaround time and outcome of the project. The repair of this essential component was approximately 30% of the cost of a new water box.
Related work

METALCLAD CeramAlloy CL+AC protects a new vertical pump column headed to an energy plant
A new 6.5-foot-diameter pump column was coated before going into service to protect it from the corrosion that destroyed its predecessor.

Art museum protects critical cooling tower support beams and piping
Two rooftop cooling towers above a museum's galleries had their corroded support beams and piping repaired and protected.
ENECON NorCal projectWinter is the time for cooling tower, chiller and heat exchanger maintenance
Before-and-after examples of cooling equipment repaired ahead of summer.
Schedule a no-cost
site visit