Emergency repair for a paper mill water box

A corroded chiller water box was rebuilt and returned in about 36 hours, at roughly 30% of the cost of a new one.

Rebuilt chiller water box finished in ENECON Blue
Rebuilt chiller water box finished in ENECON Blue.
Corroded water box with a failed divider bar before repair
Corroded water box with a failed divider bar before repair.
Divider bar area of the water box during the rebuild
Divider bar area of the water box during the rebuild.

The divider bar on a small but critical chiller water box located at a paper mill had completely corroded and was no longer functional in the process equipment it served. The mill's options to solve this problem were limited.

The lead time for a new water box was 5-6 weeks, and the mill's engineers were not willing to make emergency on-the-spot weld repairs because of safety concerns when the equipment is put back into service. ENECON was contacted to provide a solution to this emergency situation.

The water box was degreased, pressure washed, and then abrasive-blasted. METALCLAD DurAlloy and a backer plate were used to rebuild the divider bar.

One coat of METALCLAD CeramAlloy CL+AC in gray was used on the internal side, followed by a second coat in blue to finish the interior as well as the exterior of the water box.

The water box was completed and returned approximately 36 hours after it was first collected. The mill was very pleased with the turnaround time and outcome of the project. The repair of this essential component was approximately 30% of the cost of a new water box.