Wastewater treatment plant repairs and reinforces a main outfall pipe with METALCLAD DurAlloy and METALCLAD DuraWrap
A completely broken 47-inch pipe junction was re-bonded and structurally wrapped, and the outfall was commissioned in one week.


A wastewater treatment plant called on ENECON because of an unexpected break of a pipe's neck: the 47-inch-diameter glass-fiber-reinforced-plastic (GRP) junction with the main 83-inch GRP pipe. ENECON had earlier structurally reinforced the two ends of the same outfall.

This repair was much more complicated than the previous one since it was a total break causing a flood. The water level could not be lowered more than 3/4 inch below the area of the break. After divers retrieved the junction from the bottom of the water-filled manhole, ENECON technicians bonded it to the main pipe using METALCLAD DurAlloy.
They then reinforced the joint both on the inside and the outside with METALCLAD DuraWrap. DuraWrap provides structural reinforcement for pressure pipes, meeting ASME PCC-2 and ISO TS 24817 requirements, permitting the outfall to be commissioned in just one week.
Related work
Schedule a no-cost
site visit